West Lakes Gardens Drainage Improvement

Project Quick Facts

  • Estimated Completion: August 2023
  • Construction Cost: $1,819,163
  • Project Manager: Anaily Padron, P.E.
  • Project Contractor: RG Underground Engineering, Inc.
Overview

The West Lakes Gardens Drainage Improvement project is part of the Town’s comprehensive plan to mitigate flooding. The project consists of drainage system improvements in the West Lakes Gardens neighborhood.

Details

Funding Source

The West Lakes Gardens Drainage Improvement project is funded through the Stormwater Utility System Revenue Bonds Series 2021.

Contact

Thank you for your patience and cooperation as we strive to continue Growing Beautifully.

Project Manager:

Anaily Padron, P.E.

E: padrona@miamilakes-fl.gov

O: (305) 512-7133