Entry Feature NW 67 Ave

Description: This Project consists of the construction of a new entry feature on NW 67th Ave, south side of the Town, as part of the Beautification plan for the Town of Miami lakes. This Entry Feature is one of the three that were planned for FY14-15. The project will include a fountain similar to the one located on NW 154th St. and Palmetto Expressway (SR 826)

Projected Completion Date: Fall 2016

Recent Activity: As per directions by our Town Council, the Town Manager, Mr. Alex Rey, elected to have the Town act as general contractor for the project, this will drastically reduce the cost of construction, and allow the Town to choose the individual sub-contractors for the project. The subcontractor bid packages have been prepared and we are currently in the process of obtaining the prices. Construction is projected to start first week of May 2016.